by Deisy Brangman, Senior Project Manager, Brailsford & Dunlavey and Dr. Peter Noonan, Superintendent, Falls Church City Public Schools
“The
Little City” of Falls Church, Virginia, is currently making a
once-in-a-lifetime investment: It is building a new high school that will meet
the current and future vision for its top-performing school and district. That
vision includes flexibility for current and future educational programming, enrollment
growth, and continued extensive use by the community.
With any major capital improvement, a district
has to find just the right balance of community engagement. The City of Falls
Church, with a very civically involved population of over 14,000 residents in
just 2.2 square miles, stepped up to the challenge. A process involving
transparent and collaborative community engagement, as well as creative
financing and real estate transactions, has resulted in the new Heart of the
Community.
The City of Falls Church, Virginia, with
history dating back to the 1600s, is known for its urban village community,
nationally ranked K–12 International Baccalaureate (IB) public school system,
environmental activism, endless community activities, and close proximity to
Washington, DC (9 miles from City Hall to the White House).
As one of the top-ranked high schools in
Virginia (#12) and nationally (#515) by
U.S News & World Report, George Mason High School has experienced steady
enrollment growth since its opening in 1952, now serving over 800 students and with
projections estimating up to 1,500 students in the next 20–30 years. The aging facility,
and city’s only high school, no longer met the needs of the school’s progressive
and advanced academic program — the way students today learn and work together,
appropriate security features to ensure the safety of the students, and
efficient use by community groups. Falls Church City Public Schools (FCCPS)
needed a contemporary, appropriately sized high school. But how could this little
city afford such a major investment, in an area where new high school construction
costs were averaging over $100M?
In 2013, with extensive community
engagement and support, the city took the first step toward the construction of
a new, larger high school by negotiating full ownership and control of the land
from adjacent Fairfax County.
From 2014–2016, to facilitate
financial and master planning of the campus, FCCPS and the city’s General
Government established a Joint Campus Process Planning Group, Campus Joint
Steering Committee, and communications plan. Keeping the school and broader city
community informed was a priority. With the support of multiple partners — Urban
Land Institute, LINK Strategic Partners, and Perkins Eastman — the city
explored various options to achieve a modern, larger high school. That included
jointly developing the property — the private development of 10 acres and the construction
of a new high school building on the remaining 24 acres, with the existing
middle school. In 2014, the Urban Land Institute Technical Assistance Panel
(ULI TAP) analyzed and presented development options. This led to FCCPS engagement
to develop the new Shared Vision for the Schools, with one of the largest
community audiences to date.
In late
2016, it was determined that joint development would not provide the results
the community desired, and the two projects were decoupled. FCCPS initiated
design and economic feasibility efforts, leading to the identification of three
options by early 2017: partial new, renovation/addition, and build new.
Continuing with the success of the
established communications plan, and with the goal of defining the concept
vision and financial plan, FCCPS and the General Government conducted regular
meetings, surveys, and Q&A sessions to obtain input from the community, responding
publicly to all inquiries. Utilizing the listserv born from these engagements
and the PTA’s support in spreading the word, the broad community was kept
informed. Through this effort, the city secured community support for the “build
new” option that led to an overwhelming approval in late 2017 of a $120M Bond
Referendum for the construction of the future high school.
This was just the beginning.
Immediately following the Bond Referendum approval, FCCPS issued an RFP for
Design-Build Concept Proposals. In alignment with the transparent community
engagement effort, Evaluation Committees representing various community
stakeholder groups were established. FCCPS leadership knew how important the
community was, and was going to be, in the process of developing the site for the
new high school. A broad group of engaged and thoughtful community members was
key to ensuring deep ownership of the project going forward.
During this
process, FCCPS recognized that the school project was a bigger effort than it had
the in-house capacity or expertise to manage, so in early 2018 it issued an RFP
for an Owner’s Representative. Through the established selection committee
process, it ultimately hired Brailsford & Dunlavey (B&D) (supported by Hanscomb
Consulting) to advise and manage the high school project’s procurement, programming,
design, construction, and community engagement.
With B&D on board, FCCPS was now
full steam ahead. The new owner team collaborated to confirm the vision, refine
the project’s communications plan, and keep the community up to date during the
Request for Detailed Proposals process. Within just a few months, the
Design-Build team of Gilbane / Stantec / Quinn Evans Architects was selected.
With the goal of breaking ground by summer
2019, FCCPS and B&D communications teams used various platforms to reach
out to the school and broader city community to recruit participation for Design
Advisory Subcommittees for the new high school’s initial design phase. The project
team engaged in open discussions with school administration/teachers, the community,
and newly formed subcommittees, utilizing idea/comment “parking lots” and
rubrics. The team created a project email address, where any projected-related
inquiries could also be submitted. All feedback, questions, and work session work-products
were posted to the project website. Every item was addressed and responded to. One
of the key elements of success for the effort was being responsive and
adjusting to what worked and what didn’t.
Throughout the design phase, FCCPS and
the city’s General Government continued monthly Sunday Series community
meetings that provided updates on the school and economic development projects.
Concurrently, B&D’s communications team held student focus group sessions,
and the entire project team met regularly with school staff and city agencies.
This ensured all end users provided insight and that the design met the vision
and requirements of FCCPS, city building agencies, and the community.
After over 200 meetings (and
counting), the regular, collaborative, and transparent communications process
led to a forward-looking design for the new school. It would be a sustainable campus
with contemporary educational concepts, including collaboration areas in a
variety of sizes, maker spaces, fabrication labs, variable intensity learning
labs, flexible-use learning studios, appropriately sized performing arts and
athletic facilities, provisions for use of the school by community groups
(e.g., band, theatre, recreation, civic meetings, weekend school),
sustainability, and a way to recognize the history, alumni, and supporters of
the school.
Additionally, the incorporation of system
and building zones will allow for the shared or partial use of the facility while
maintaining safety, security, and energy efficiency. Another feature: an innovative
structural grid accommodates future changes in programming and enrollment and provides
an open and visibly connected learning environment that encourages
collaboration among all of its users. Finally, the building is designed to
achieve LEED® Gold certification and Net Zero Energy through the use of
geothermal wells, photovoltaic panels, and energy-efficient MEP systems. Truly
the new Heart of the Community.
The story of the new George Mason High
School is a complex, but carefully planned puzzle. Ultimately, though, establishing
and following through with a clear, transparent community engagement plan has
been and continues to be the key to a successful project. Stay tuned for
updates when we open in 2021!
Dr. Peter Noonan
serves as the Superintendent of Falls Church City Public Schools. He began his
career as a special education teacher in New Mexico, and previously worked with
Fairfax City and Fairfax County Public School systems as Superintendent,
Assistant Superintendent, principal, and assistant principal.
Ms. Deisy
Brangman serves as a Senior Project Manager for Brailsford & Dunlavey. In
this role, she has led multiple project and program management teams overseeing
public school district capital project portfolios totaling over $4B in
Washington, DC; Alexandria City, VA; Falls Church City, VA; and Prince George’s
County, MD.